A tunnel project ordered by LH in Gwangju’s Hyocheon district has become a four-year dispute over design changes, stalled construction and unpaid overhead costs. The 680-meter underpass was contracted in February 2017 for 13.875 billion won, began construction that April and was originally due for completion in October 2019. Completion was pushed to August 2023 as the design and construction method were repeatedly revised.

The initial reinforced-concrete design required a working area that made it difficult to secure a temporary detour and created a height difference beside nearby shops. LH later changed the plan to an H-shaped precast-concrete method, raising the contract value to 17.22433 billion won. That design left the road level 76 centimeters higher than the existing road, prompting residents to warn that the change could sever the village. LH then directed another change to a steel-pipe precast method, leaving the site idle for more than two years.

The final construction cost reached about 26.2 billion won. The contractor is suing LH over salaries, insurance premiums, accommodation and other indirect costs incurred while workers remained assigned during the suspension. LH has said it would recognize 1.368 billion won for the main and subcontractors, while the contractor revised its claim from 4.58 billion won to 3.619 billion won. A court appraisal reportedly found that at least 2.254 billion won would be payable even under LH’s calculation method.

LH said negotiations over the road level and surrounding terrain extended the schedule after the land development changed local conditions. Allegations that redesign costs were shifted to the contractor and that document preparation was pressured remain disputed. The Gwangju District Court’s Haenam branch is scheduled to issue its first ruling on December 9, leaving liability and the final payment unresolved.