Pohang faces a narrowing timetable for replacing its waste treatment capacity. Direct landfilling of household waste is scheduled to end in 2030, under revised waste management rules that require combustible household waste to be incinerated first. Only incombustible material and incineration ash may then be landfilled.
The pressure increases in February 2034, when the 15-year operating and management right for the household waste energy recovery facility in Hodong, Nam-gu, ends. The facility currently handles about 184 tonnes a day, roughly 40 percent of Pohang’s combustible waste. If a replacement incinerator is not operating by then, the city could need to send about 200 tonnes of bagged waste a day outside the area. Other municipalities may reject that waste because their own treatment capacity is limited.
The proposed Pohang Eco Village complex is budgeted at 638.4 billion won, with 30 percent from the national government and 70 percent from local funds. Large environmental facilities typically require site selection, feasibility work, an environmental impact assessment, compensation and construction. The supplied report estimates that these steps take at least seven to eight years, leaving little room for delay.
Even on the current timetable, the existing facility could close about 11 months before a new facility is completed. That interval would represent an estimated 50,000 tonnes of combustible waste requiring an alternative treatment route. The project therefore depends not only on construction, but also on completing a residents’ support council, an urban planning decision, a local financial investment review, compensation and environmental consultations before a target start of construction in January 2031. The evidence identifies a serious risk of a treatment gap if the project slips, but it does not establish that the gap will occur.