A transport ministry accident investigation committee has blamed the collapse during construction of the Bujeon–Masan Line’s Nakdong 1 Tunnel on an unverified grouting method and excessive injection pressure, rather than poor ground conditions. Investigators said SK ecoplant did not review possible effects on existing underground structures or conduct trial construction to set safe pressure and volume, while the injected grout damaged structures and cracked tunnel segments.
Water leaks and soil loss continued, but work was not halted for analysis, which investigators said also contributed to the accident. The ministry is reviewing safer construction plans for two evacuation passages that have not yet begun construction.