A planned semiconductor cluster in southwestern Korea is being built around a demanding sequence: four memory-chip production lines at the former Gwangju Military Airport site, with first mass production targeted for June 2030. The current schedule assigns design and permitting to 2027, construction to 2028, and completion to the end of 2029.

A policy forum identified electricity, industrial water and site handover as conditions that must move in step with construction. The first power phase is planned to provide 3.1 gigawatts by the end of 2028, with a long-term expansion to 6.3 gigawatts. Water supply is initially targeted at 150,000 tonnes a day, while the broader plan combines corporate demand of 650,000 tonnes with a reserve of 410,000 tonnes, reaching as much as 1.06 million tonnes a day.

The figures remain a plan rather than proof of secure supply. Experts called for testing whether the Yeongsan and Seomjin river basins could maintain household, agricultural and industrial supplies during extreme drought. They also proposed agreeing on priority uses in advance and increasing water reuse inside the plants.

The airport relocation, site delivery and industrial-complex construction will also require joint schedule management. A government and local-authority implementation agreement was proposed to document responsibilities, funding and deadlines. Before equipment arrives, the electricity and water systems need supply-date and quality verification, while responsibilities for uninterrupted power and renewable energy must be assigned. Disputes over reservoirs and transmission routes, compensation, and opportunities for local companies in procurement and testing remain part of the project’s preparation.